伦敦火车站电梯设备升级进度

时间:2018-01-29 08:28来源:新电梯中国 作者:译文 Jade
  新电梯中国网讯

  近日,伦敦交通运输局发出报道,公布关于数个火车站电梯设备升级进度的细节。其中,帕丁顿站的两台自动扶梯的台阶、链条、踏板及扶手已经就绪,新电梯也准备投入测试;邦德街站的电梯设备准备工作也已经就绪;骑士桥站的自动扶梯的安装工作已经在站口展开,电梯的安装也已经开始;最后,卡姆登镇站的自动扶梯翻新工程也已经展开,预计今年三月能完成一台,另一台会稍晚些。

  PROGRESS NOTED ON VT UPGRADES AT LONDON RAIL STATIONS

  A newly released report from Transport for London details the progress made on rail-station vertical-transportation (VT) upgrades at several stops. At Paddington Station, the steps, chains, floorplates and handrails of two new escalators are complete, and a new elevator is ready for testing. At the Bond Street station, preparatory work on VT for a "step-free interchange" to the Elizabeth line has been completed. At the Knightbridge station, work has begun on two new station entrances and elevators. And, at the Camden Town station, refurbishment on two escalators has begun, with the first to be ready in early March and the second later this year.

TAG标签:
本文网址:https://www.xindianti.com/html/diantizixun/guojishidian/20180129/620169.html
新电梯中国网曝料热线:13703160955;Email:dll@xindianti.com;admin@cnlift.cn
QQ:270206927; 新电梯QQ交流群:82958246; 微信公众号:新电梯

  免责声明:本文仅代表作者个人观点,不代表新电梯网媒观点,真实性、完整性、及时性等本站不作任何保证或承诺,请读者仅作参考,并请自行核实相关内容。如需转载,请注明文章作者和来源。
  Disclaimer: This article only represents for the author's opinion and is only offered for reference. New Elevator China doesn't guarantee truth, completeness and timeliness of the article. The readers may confirm detail of the article from its original source.Please give clear indication of the author and original source of the article if any copy is needed.
------分隔线----------------------------

新 闻 推 荐

cheap louis vuitton fake bags authentic beats by dre pro box air jordan 11 dmp gold eyelets new balance 574 review